Here are some key highlights:
- Successfully completed over 75,000 work hours with zero lost-time injuries.
- 560MVA Transformer manufactured and installed in less than 12 months.
- 586MVA Generator and 414MW Turbine manufactured and installed within 24 months.
- Delivered over 1,400 tons of equipment to site.
- Three chartered Heavy Lift Vessels transported equipment from Yokohama to Gladstone.
- Two super loads, each weighing 665 tons and measuring 116 metres by 6 metres travelled the 314km Gladstone to Callide Power station passing through Rockhampton, Dululu and Banana.
- Eleven oversized loads were transported from Gladstone to Callide C Power station.
- Two complex 260-ton lifts were executed, involving transfers between Gantry and Crawler Cranes.
Projects of this scale and complexity are only achievable through the skill and commitment of every team involved.