This complex project involved the replacement of the High Pressure and Low Pressure turbines, the Generator, and Generator Transformer, underscoring the immense effort and dedication of everyone involved.

Here are some key highlights:

- Successfully completed over 75,000 work hours with zero lost-time injuries.
- 560MVA Transformer manufactured and installed in less than 12 months.
- 586MVA Generator and 414MW Turbine manufactured and installed within 24 months.
- Delivered over 1,400 tons of equipment to site.
- Three chartered Heavy Lift Vessels transported equipment from Yokohama to Gladstone.
- Two super loads, each weighing 665 tons and measuring 116 metres by 6 metres travelled the 314km Gladstone to Callide Power station passing through Rockhampton, Dululu and Banana.
- Eleven oversized loads were transported from Gladstone to Callide C Power station.
- Two complex 260-ton lifts were executed, involving transfers between Gantry and Crawler Cranes.

Projects of this scale and complexity are only achievable through the skill and commitment of every team involved.
Media Share